WGCT PROJECT REPORT
1. The project is completed but not paid for yet. We still need $9,000 to pay the remaining bills.
2. The transmitter and antenna have been removed from the old Tower.
3.The antennas have been inspected and repaired.
4. The power divider was delivered on March 26.
5. The 1000 watt transmitter was Delivered and installed.
6. We are receiving wonderful reports from as far away as Circleville, Washington Court House, Newark, Lancaster. WOW !!!!
At present $21,000 has already been collected and paid on the project.
PRAISE GOD WE ARE TWO THIRDS OF THE WAY THERE
The total project cost was $30,000.
Please help us pay off the bills for the project.
To Donate go to www.coacb.org/request.htm